Replenishment Scenario 1 - Planning Forecast with Discrete PO, Version 1.0 
Status:  Provisional Ratification by Committee November 2000.
Recast of Pre-2000 Version C Order Models (Balloted and Ratified by Membership, November 1996) and Version A Forecast Models and (Balloted and Ratified by Membership, August 1997)

Process Activities

Special Notes:                   

 


Activity Diagram (See also Narrative):

Replmodl1_activity.jpg (62268 bytes)

 


Narrative (see also Graphic):

Step Description
1. The buyer run Material Requirements Planning (MRP) process. Buyer nets MRP data to generate a planning forecast and determine whether replenishment is required during the current planning cycle.
2. If buyer determines that replenishment is required during the current planning cycle, buyer sends Purchase Order per Order Model 1.
3. Buyer generates planning forecast to send to supplier per Forecast/Planning Model 1.   Planning Forecast is typically regenerated weekly. Any changes/exceptions from a previous run are factored into the new generation of the planning forecast.  The seller responds to the forecast if needed.
4. Prepare for the next MRP run. If there are changes arising out of a supplier's response to a forecast, they are dealt with during this activity, then the next generation of the forecast starts again with 'Process MRP.'